JJM Construction Ltd. was the managing partner of this Joint Venture with Geopac Inc. JJM oversaw contract administration, site coordination, survey, and site safety, security, and maintenance. Together we carried out the Ground Improvement and Utilities Relocation project for Metro Vancouver at the Annacis Island Wastewater Treatment Plant. 


JJM crews carried out large scale excavation and materials handling, access road construction, major utility relocations, and contaminated soils remediation. JJM also managed the work of the electrical subcontractor for the upgrades to the power feed infrastructure and the installation of the JJM-supplied 2,500 kVA back-up generators. JJM provided support services to Geopac for the stone column and cutter soil mix (CSM) ground improvement installations, and oversaw the installation and monitoring of state-of-the-art, automated settlement and vibration monitoring systems.

Careful coordination with plant operations personnel was required to ensure no interruptions to treatment processes; careful sequencing and staging of work ensured a minimum of disruptions to, or impacts on, surrounding residents and businesses.

Westminster Highway Culvert Replacement

Hard Ground Dredging & Sediment Remediation

South Delta Main No. 1 Replacement Phase 2

SeaBus Maintenance Dock Temporary Berth

Road Rail Utility Corridor, Ridley Island

Diavik Dike Foundation Preparation

Coquitlam UV Disinfection Plant

Fraser River Forcemain Crossing – Land Portion

Middle Harbour Fill Site Remediation